100Days/Sprint2: Difference between revisions
From Maemo Wiki
Jump to navigationJump to search
imported>qgil |
imported>qgil →Old tasks: reshaped |
||
| Line 5: | Line 5: | ||
* Next IRC sprint meeting scheduled on 2008/07/22, see [[100Days/Sprint3]]. | * Next IRC sprint meeting scheduled on 2008/07/22, see [[100Days/Sprint3]]. | ||
== | ==Tasks== | ||
{| class="wikitable sortable" | |||
|- | |||
! Committed | |||
! Task | |||
! Owner | |||
! Completion | |||
! Highlights | |||
|- | |||
| 2008-05-10 || Who's who in Maemo || Dave || % || Discussion on implementation details pending || | |||
|- | |||
| 2008-05-10 || Companies involved in Maemo development || Dave || % || Initial group of companies defined || | |||
|- | |||
| 2008-06-10 || [[Task:Consolidation of Extras|Consolidation of Extras]] || Niels || 0% || Niels must specify what goes in this sprint || | |||
|- | |||
| 2008-06-10 || Extras % maemo.org/downloads integration || Niels || % || Complete and/or document in wiki page || | |||
|- | |||
| 2006-06-10 || Registration and sponsorship for [[Maemo summit 2008]] || Oskari/Bergie || % || About to release || | |||
|- | |||
| 2008-06-10 || [[User:Peterschneider|Update maemo.org/intro]] || Dave || % || Just few pages waiting to be moved || | |||
|- | |||
| 2008-06-10 || Better extras categories and debtags || Niels || % || Proposal needs to be drafted in wiki page || | |||
|- | |||
| 2008-06-10 || Put the [[Bugsquad]] in place || Andre/Karsten || % || See [http://lists.maemo.org/pipermail//maemo-developers/2008-June/033719.html this mail] || | |||
|- | |||
| 2008-06-10 || Forum interface to mailing lists released || Oskari/Bergie || % || Beta to be made public for testing || | |||
|- | |||
| 2008-06-10 || User profile improvements defined and started || Oskari || % || ? || | |||
|- | |||
| 2008-06-10 || No pages remaining in [[:Category:Midgard wiki]] || Dave || % || The target is actually the end of July || | |||
|- | |||
| 2008-06-30 || [[Task:Maemo brand|Maemo brand]] || Quim || 90% || Ready for approval. Waiting feedback || | |||
|- | |||
| 2008-06-30 || [[Task:Sprint progress|Sprint progress]] || Quim || 20% || Setting up the process || | |||
|- | |||
| 2008-06-30 || [[Task:Components and packages|Components and packages]] || Soumya || % || Briefing Soumya-Quim made || | |||
|- | |||
| 2008-06-30 || Visit c-base for [[Maemo Summit 2008]] plan || Quim || 10% || Visit confirmed with Haustier and Trip booked || | |||
|} | |||
== New in this sprint == | == New in this sprint == | ||
Revision as of 17:47, 1 July 2008
Planning
- Kick-off meeting organized in the Freenode #maemo-meeting IRC channel on 2008/06/30 at 18:00 UTC.
- The meeting log contains also the review of the last sprint.
- Current sprint progress. (alpha)
- Next IRC sprint meeting scheduled on 2008/07/22, see 100Days/Sprint3.
Tasks
| Committed | Task | Owner | Completion | Highlights | |
|---|---|---|---|---|---|
| 2008-05-10 | Who's who in Maemo | Dave | % | Discussion on implementation details pending | |
| 2008-05-10 | Companies involved in Maemo development | Dave | % | Initial group of companies defined | |
| 2008-06-10 | Consolidation of Extras | Niels | 0% | Niels must specify what goes in this sprint | |
| 2008-06-10 | Extras % maemo.org/downloads integration | Niels | % | Complete and/or document in wiki page | |
| 2006-06-10 | Registration and sponsorship for Maemo summit 2008 | Oskari/Bergie | % | About to release | |
| 2008-06-10 | Update maemo.org/intro | Dave | % | Just few pages waiting to be moved | |
| 2008-06-10 | Better extras categories and debtags | Niels | % | Proposal needs to be drafted in wiki page | |
| 2008-06-10 | Put the Bugsquad in place | Andre/Karsten | % | See this mail | |
| 2008-06-10 | Forum interface to mailing lists released | Oskari/Bergie | % | Beta to be made public for testing | |
| 2008-06-10 | User profile improvements defined and started | Oskari | % | ? | |
| 2008-06-10 | No pages remaining in Category:Midgard wiki | Dave | % | The target is actually the end of July | |
| 2008-06-30 | Maemo brand | Quim | 90% | Ready for approval. Waiting feedback | |
| 2008-06-30 | Sprint progress | Quim | 20% | Setting up the process | |
| 2008-06-30 | Components and packages | Soumya | % | Briefing Soumya-Quim made | |
| 2008-06-30 | Visit c-base for Maemo Summit 2008 plan | Quim | 10% | Visit confirmed with Haustier and Trip booked |
New in this sprint
- Official review of Task:Maemo brand, a task that is in fact completed - Quim
- Improvements on Task:Sprint progress, or at least progress reporting. - Quim
- Task:Components and packages that define Maemo - Soumya
- Finalise selection process for new logo - Dave
- Visit c-base and confirm the basic Maemo Summit plan. - Quim
- All component owners of product Website in charge, with all bugs triaged with right priority/severity - Andre
Bugs in product Website
The bugs assigned in the last sprint meeting are marked as HIGH. The bugs proposed for the next sprint are marked as MEDIUM. Only product/component maintainers can change this status. Comment on a bug if you want to push it up. Check also those marked as EASYFIX.
What follows are the bugs that have special attention/progress.
- Bugzilla
Maintainer: Karsten, Ferenc
- Documentation
Maintainer: Dave
Bug #95: desktop-files documented poorly- Bug #101: Use the wiki for developer documentation - Now in the hands of Maemo SW team.
- Downloads
Maintainer: Niels Breet
- Garage
Maintainer: Marcell, Ferenc
- Bug #3264: Garage is (re)sending a "maemo logo competition" mail every hour
- Bug #3354: Publishing packages to garage.maemo.org oftens results in "lost connection" and "permission denied" from scp
- General
Maintainer: Marcell
- News
Maintainer:
- Repository
Maintainer: Marcell Lengyel, Niels Breet
- Wiki
Maintainer: Ferenc
- Bug #3283: Install the citation extension for the wiki
- Bug #3341: Install the Category Tree extension for the wiki
- Bug #3342: Install the Dynamic Page List extension for the wiki
Backlog
Moved to 100Days/Sprint3#Backlog
Proposals
Moved to 100Days/Sprint3#Proposals