| 2008-01-07 || Plan to redesign Downloads and add functionality || Niels ||30% || Need to pick ideas to commit to in next Sprint
| 2008-01-07 || Plan to redesign Downloads and add functionality || Niels ||30% || Need to pick ideas to commit to in next Sprint
|-
| 2009-02-04 || [https://bugs.maemo.org/show_bug.cgi?id=3846 List Maemo Bugzilla custom code changes] || Andre || 30% || ...in order to port maemo.org Bugzilla to a more recent codebase (long term). See bug report and [[User:Andre/bug3846|diff dump]] for more details.
|}
|}



Revision as of 14:55, 4 February 2009

February 2009 Sprint planning

Tasks

Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.

Completed Good progress Just standing Some help needed! Really stuck/delayed
Committed Task Owner % Highlights
2008-09-30 Task:Reducing number of external repositories Niels 40% Contacted most owners. Had a lot of positive responses, but need to gently push most of them again..
2008-09-30 Task:Open Source Proof Points Quim 5% Nothing done in this sprint, sigh.
2008-11-04 Karma for applications Hirvinen 0%
2008-11-04 Finalise layout for maemo.org/support Dave & Tim 70% Wireframe and content done. Awaiting design by Glaubert.
2008-11-04 Task:Texts for maemo.nokia.com Quim 20% Drafted the "Open Source" part, but need to complete out of this sprint.
2008-11-04 Define what is needed to get git up on maemo.org Tero 80% Talk page up at Git for garage, Plans up at Git For Garage. 80% because discussion still takes place. But nothing stopping from moving ahead.
2008-12-03 Task:Implement new maemo.org layout and style Henri/Niels 20%
2008-12-03 Objective:Community localization Quim 10% Objective roadmapped in Harmattan, all details need to be figured out
2008-01-07 Plan to redesign Downloads and add functionality Niels 30% Need to pick ideas to commit to in next Sprint
2009-02-04 List Maemo Bugzilla custom code changes Andre 30% ...in order to port maemo.org Bugzilla to a more recent codebase (long term). See bug report and diff dump for more details.

Bugs in product Website

The bugs assigned in the last sprint meeting are marked as HIGH. The bugs proposed for the next sprint are marked as MEDIUM. Only product/component maintainers can change this status. Comment on a bug if you want to push it up. Check also those marked as EASYFIX.

What follows are the bugs that need special attention/progress.

For the record:

{{#bugzilla:id=1660,2179,3177,3178,3432,3562,3767,3788,3794,3796,3846

 |columns=id,severity,product,status,resolution,summary,to

}}

Activity log

Latest activity report goes on top.