Revision as of 12:40, 15 January 2010
January 2010 Sprint planning
- Planning meeting: Tuesday, 5th January 14:30 UTC in #maemo-meeting.
- Follows December 09. Precedes February 10.
Tasks
Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.
| Completed | Good progress | Just standing | Some help needed! | Really stuck/delayed |
| Task ID | Task | Sprint priority | Owner | Percentage complete | Notes |
|---|---|---|---|---|---|
| 9.10-07 | Server migration | Must | Ferenc | 90% | The only server left is scratchbox.org. |
Actions
None yet
Activity log
Latest activity report goes on top. Activity will be reported here, Qaiku #maemork channel (Atom feed) or talk.maemo.org.